Goods hoist

Lifting a goods hoist up on top of the roof for it to be assembled, 3rd floor and 10 metres into the building.

PXL_20220420_110731471

PXL_20220420_110731471

PXL_20220420_110711223

PXL_20220420_110711223

PXL_20220420_111404694

PXL_20220420_111404694

PXL_20220420_111102627

PXL_20220420_111102627

Fire suppression installation 

fire suppression systems were not installed in time by the engineers on site, so our solution was to take out part of the roof, lift into the roof void and place each fire suppression control box into there final position.

4 in total were lifted and placed over 3 days, each a different location in the warehouse

PXL_20220307_122300990

PXL_20220307_122300990

IMG-20220301-WA0040

IMG-20220301-WA0040

IMG-20220301-WA0036

IMG-20220301-WA0036

IMG-20220301-WA0029

IMG-20220301-WA0029

IMG-20220301-WA0052

IMG-20220301-WA0052

IMG-20220301-WA0051

IMG-20220301-WA0051

IMG-20220301-WA0048

IMG-20220301-WA0048

IMG-20220301-WA0043

IMG-20220301-WA0043

PXL_20220307_122518927

PXL_20220307_122518927

IMG-20220301-WA0042

IMG-20220301-WA0042

London City Airport

Steel frame work needed to be installed into the 4th floor, but there was no access from the ground.

Our solution to the problem was lift up to the 6th floor and hoist down into the 4th and help with installation.

Dismantling Scaffolding

Dismantling and removing scaffolding from a fourth floor rooftop

The main use of the Hiab during the project was lifting down the twenty-one metre support beams.

The Hiab and our team also assisted in lifting down other scaffolding materials.

The work took four team members two days to complete.

20210802_120320

20210802_120320

20210802_083440

20210802_083440

20210802_085112

20210802_085112

20210802_121903

20210802_121903

20210802_121140

20210802_121140

20210802_115914

20210802_115914

20210802_120847

20210802_120847

20210802_121113

20210802_121113