top of page
Glass 'n' Drones

Lifting large 3x3m sliding glass door panels over 30m with a hydraulic glass sucker. Photos and videos recorded by drone. 

IMG-20240515-WA0008

IMG-20240515-WA0008

IMG-20240515-WA0007

IMG-20240515-WA0007

IMG-20240515-WA0013

IMG-20240515-WA0013

IMG-20240515-WA0010

IMG-20240515-WA0010

IMG-20240515-WA0004

IMG-20240515-WA0004

IMG-20240515-WA0011

IMG-20240515-WA0011

Carbon capture unit part 2

Rolling, lifting and positioning of a 3 tonne vessel. With only 1m spare at the tallest point.

20240320_115121

20240320_115121

20240320_134830

20240320_134830

20240320_152239

20240320_152239

20240320_150812

20240320_150812

Bankside Substation

Lifting 500kg fan units for a substation at the Tate Modern in London, lifting at over 20m high and 10m into the building.

with only 1m of leg on the lifting side, it was quite challenging conditions for the team, but with perfect planning with out RaM's package, it was a breeze. 

PXL_20240318_100316960

PXL_20240318_100316960

PXL_20240318_100259102

PXL_20240318_100259102

PXL_20240318_093700036

PXL_20240318_093700036

Climbing Frame Catastrophe

Assisting in felling a 25m oak tree that had fallen onto another tree endangering a children's climbing frame in a public park. Lifting limbs and branches one by one down and off the oak as the tree surgeons removed them. 

The main trunk once pruned was over 20 metres tall and weighed over 4,000kg,  needed to be carefully lowed down as there was no where it could be felled without causing damage to the surrounding park. 

PXL_20240111_104925872

PXL_20240111_104925872

PXL_20240111_102106598

PXL_20240111_102106598

18m Steel Beam!

Lifting an enormous structural steel beam into position after a lorry strike.

Our solution was to position the beam under the structure then move the Haib to lift the beam directly up and into the final position. slotting it into the building and onto the podium at the same time.

Once the beam was secure we then lifted the roof structure to remove he temporary supports and then lower each part down onto the secure beam.

PXL_20231003_073223101

PXL_20231003_073223101

PXL_20231003_073259393

PXL_20231003_073259393

PXL_20231003_073851553

PXL_20231003_073851553

PXL_20231003_073848274

PXL_20231003_073848274

PXL_20231003_073834678

PXL_20231003_073834678

PXL_20231003_074200073.PANO

PXL_20231003_074200073.PANO

PXL_20231003_093948316

PXL_20231003_093948316

PXL_20231003_093829571

PXL_20231003_093829571

PXL_20231003_095528815

PXL_20231003_095528815

PXL_20231003_095530674

PXL_20231003_095530674

Indoor lifting

An indoor carbon capture machine, needed to be transported and then lifted into position. over 3 days our team loaded, delivered and placed each section indoors,

using spreader bars to keep the load secure with out damaging the fragile parts of the machine.

1st Section pt1

1st Section pt1

1st Section pt2

1st Section pt2

2nd Section pt1

2nd Section pt1

2nd Section pt2

2nd Section pt2

Top Section pt1

Top Section pt1

Top Section pt2

Top Section pt2

Top Section pt3

Top Section pt3

Gantry and Carrier

Serval air handling units needed to be moved into position at Maidstone hospital but the area was not accessible by road or Hiab, while a crane would cause to much disruption to the hospital.

Our solution was to use our gantry and tracked carrier in combination to manoeuvre the units into position with zero disruption to the hospital or the patients.

IMG-20230616-WA0012

IMG-20230616-WA0012

IMG-20230616-WA0004

IMG-20230616-WA0004

IMG-20230616-WA0003

IMG-20230616-WA0003

IMG-20230616-WA0007

IMG-20230616-WA0007

IMG-20230616-WA0005

IMG-20230616-WA0005

Mission impossible?

19ft Swim Spa needed to be lifted over 50m with no access.

Our solution, including crane lifting, moving on our tracked carrier and lifting with our gantry system. 

the operation was undertaken over 2 days and using 3 members of our team.

Give us a call to discuss your mission impossible!

20230217_094343

20230217_094343

20230217_095310

20230217_095310

IMG-20230220-WA0000

IMG-20230220-WA0000

IMG-20230220-WA0001

IMG-20230220-WA0001

20230217_095848

20230217_095848

Swim Spa move

17ft Swim spa moved with ease on our tracked carrier!

Saving on labour, over rough terrain and lining up perfectly to be lifted off with our gantry system.

Call Peter for more information on how the tracked carrier can be your tight access solution.

Airport Tug

An airport tug needed to be unloaded by crane, but with an inconvenient crane permit waiting time of sixteen weeks, our solution involved expert operators using three of our large Hiabs in a tandem lift. 

give us a call to discuss your lifting solution.

PXL_20220707_133500821

PXL_20220707_133500821

lifting off of trailer

lifting off of trailer

PXL_20220707_133107614

PXL_20220707_133107614

landing the tug

landing the tug

Goods hoist

Lifting a goods hoist up on top of the roof for it to be assembled, 3rd floor and 10 metres into the building.

lifting off of lorry bed

lifting off of lorry bed

PXL_20220420_110711223

PXL_20220420_110711223

up to the 3rd floor

up to the 3rd floor

landing into final postion

landing into final postion

Fire suppression installation 

fire suppression systems were not installed in time by the engineers on site, so our solution was to take out part of the roof, lift into the roof void and place each fire suppression control box into there final position.

4 in total were lifted and placed over 3 days, each a different location in the warehouse

PXL_20220307_122300990

PXL_20220307_122300990

IMG-20220301-WA0040

IMG-20220301-WA0040

IMG-20220301-WA0036

IMG-20220301-WA0036

IMG-20220301-WA0029

IMG-20220301-WA0029

IMG-20220301-WA0052

IMG-20220301-WA0052

IMG-20220301-WA0051

IMG-20220301-WA0051

IMG-20220301-WA0048

IMG-20220301-WA0048

IMG-20220301-WA0043

IMG-20220301-WA0043

PXL_20220307_122518927

PXL_20220307_122518927

IMG-20220301-WA0042

IMG-20220301-WA0042

London City Airport

Steel frame work needed to be installed into the 4th floor, but there was no access from the ground.

Our solution to the problem was lift up to the 6th floor and hoist down into the 4th and help with installation.

Dismantling Scaffolding

Dismantling and removing scaffolding from a fourth floor rooftop

The main use of the Hiab during the project was lifting down the twenty-one metre support beams.

The Hiab and our team also assisted in lifting down other scaffolding materials.

The work took four team members two days to complete.

20210802_120320

20210802_120320

20210802_083440

20210802_083440

20210802_085112

20210802_085112

20210802_121903

20210802_121903

20210802_121140

20210802_121140

20210802_115914

20210802_115914

22 metre ridge beam

22 metre ridge beam

20210802_121113

20210802_121113

bottom of page