
Goods hoist
Lifting a goods hoist up on top of the roof for it to be assembled, 3rd floor and 10 metres into the building.
![]() PXL_20220420_110731471 | ![]() PXL_20220420_110711223 |
---|---|
![]() PXL_20220420_111404694 | ![]() PXL_20220420_111102627 |
Fire suppression installation
fire suppression systems were not installed in time by the engineers on site, so our solution was to take out part of the roof, lift into the roof void and place each fire suppression control box into there final position.
4 in total were lifted and placed over 3 days, each a different location in the warehouse.
![]() PXL_20220307_122300990 | ![]() IMG-20220301-WA0040 |
---|---|
![]() IMG-20220301-WA0036 | ![]() IMG-20220301-WA0029 |
![]() IMG-20220301-WA0052 | ![]() IMG-20220301-WA0051 |
![]() IMG-20220301-WA0048 | ![]() IMG-20220301-WA0043 |
![]() PXL_20220307_122518927 | ![]() IMG-20220301-WA0042 |
London City Airport
Steel frame work needed to be installed into the 4th floor, but there was no access from the ground.
Our solution to the problem was lift up to the 6th floor and hoist down into the 4th and help with installation.
Dismantling Scaffolding
Dismantling and removing scaffolding from a fourth floor rooftop.
The main use of the Hiab during the project was lifting down the twenty-one metre support beams.
The Hiab and our team also assisted in lifting down other scaffolding materials.
The work took four team members two days to complete.
![]() 20210802_120320 | ![]() 20210802_083440 |
---|---|
![]() 20210802_085112 | ![]() 20210802_121903 |
![]() 20210802_121140 | ![]() 20210802_115914 |
![]() 20210802_120847 | ![]() 20210802_121113 |